The Construction Calendar for the Spring 2010 Build will be updated.
Any part of the schedule is subject to change without notice.
| Number | ||||||
| Day & | of | |||||
| Time | Date | Volunteers | Description of Work | Notes | ||
| Week Of: |
| Subcontractor Item | ||||
| Week Of: | Temporary Power Set By Electrician | Subcontractor Item | ||||
| Week Of: | Sewer & Water & Natural Gas Roughed In & Concrete Capped | Subcontractor Item | ||||
| Week Of: | Beam, Sill and Capping Materials Delivered To Site | Supplier | ||||
| Wednesday | 10 | 1. Build and Set Support Beam | Volunteers: | |||
| 5:30 - Dark | 2 | 2. Cut, Drill and Set Treated 2x6 Sill material | ||||
| Saturday | 10 | 1. Cut and Place Rim and Floor Joists | ||||
| 9:00 - 5:00 | 10 | 2. Cut, Glue and Place Floor Sheathing as Joist Progress Allows | ||||
| Week Of: | Walls, Top Plate, Bracing & Other Related Materials Delivered To Site | Supplier | ||||
| Tub Surround Delivered To Site | Plumber | |||||
| Wednesday | 10 | Unpack walls and arrange for Saturday work | Volunteers: | |||
| 5:30 - Dark | 12 | 1. Begin setting exterior walls (done by Noon) | ||||
| 3 | 2. Begin setting interior walls (done by 3PM) 3. Brace & Top Plate walls as they are set | |||||
Saturday |
| 6 | 1. Wrap Home with Tyvek | |||
| 9:00 - 5:00 | 2 | 2. Mark Truss Locations | ||||
| Week Of: | Roof Trusses & Sheathing Delivered To Site | Supplier | ||||
| Week Of: | Homeowner Selects Roofing, Counter, Exterior Door and Siding Colors | Homeowner | ||||
| Wednesday | Volunteers: | |||||
| 5:30 - Dark | TBD | |||||
| Saturday | 10 | 1. Install Roof Trusses | ||||
| 9:00 - 5:00 | 10 | 2. Cap Walls | ||||
| Week Of: | Roofing Materials, Doors & Windows Delivered To Site | Supplier | ||||
| Week Of: | Electrician Roughs In Box and Garage Wiring | Subcontractor | ||||
| Wednesday | 10 | 1. Sheath Roof | Volunteers: | |||
| 5:30 - Dark | 12 |
| ||||
| [ 2. Install Three Doors (one door per two people) Install Windows] | ||||||
| Saturday | 16 | 1. Roof entire project | ||||
| 9:00 - 5:00 | ||||||
| Week Of: | Siding and Soffit Materials & Sheetrock Delivered To Site Garage | Supplier | ||||
| Week Of: | Electrician & Plumber Roughs In Entire Home | Subcontractors | ||||
| Wednesday | 8 | 1. Set Vinyl Trim Pieces On Home | Volunteers: | |||
| 5:30 - Dark | 10 | 2. Drywall Garage Ceiling & Walls | ||||
| Saturday | 10 | 1. Hang vinyl siding on entire home | ||||
| 9:00 - 5:00 | 2 | 2. Install Garage Overhead Door | ||||
| Week Of: | Insulation & related materials delivered to Site Garage | Supplier | ||||
| Wednesday | 8 | 1. Wall Insulation Installed | Volunteers: | |||
| 5:30 - 9:00 | 4 | 2. Vapor Barrier Stapled to Walls | ||||
| Saturday | 4 | 1. Finish Soffit - Right Away at 9:00 | Volunteers:
| |||
| 9:00 - 5:30 | 12 | 2. Sheetrock Ceilings - Start After Lunch | ||||
| 8 | 3. Start Sheetrocking Walls | |||||
| Wednesday | 12 | 1. Finish Sheetrocking Walls | Volunteers: | |||
| 5:30 - 9:00 | ||||||
| Saturday | 6 | 1. Blow In Insulation | Volunteers: | |||
| 9:00 - 5:00 | 8 | 2. Dispose of Garbage & Construction Scraps | ||||
| 4 | 3. Complete Cleaning of Property | |||||
| Week Of: | Flooring Materials Delivered To Site Garage | Flooring Supplier | ||||
| Week Of: | Kitchen & Bathroom Cabinets Delivered To Site Garage | Cabinet Supplier | ||||
| Week Of: | Countertop & Vanity Top Delivered To Site Garage | Supplier | ||||
| Week Of: | Interior Doors and Trim Delivered To Site Garage | Millwork Supplier | ||||
| Week Of: | Drywall Taped and Textured | Subcontractor | ||||
| Saturday | 10 | 1. Interior Walls Painted | Volunteers: | |||
| 9:00 - 5:00 | ||||||
| Wednesday | 8 | 1. Interior Doors Hung | ||||
| 5:30 - 9:00 | 4 | 2. Window Trim Installed | ||||
| Week Of: | Flooring Installed in Entire Home | Contractor Critical Date! | ||||
| Saturday | 6 | 1. Floor Trim Installed | Volunteers: | |||
| 8:00 - 4:00 | 2 | 2. Misc. Bathroom Fixtures, Doors and Bars Installed | ||||
| 2 | 3. Kitchen Cabinets Hung & Appliances Installed | |||||
| 2 | 4. Counter top installed |